BK Enterprise Inc. has successfully submitted the 100% design package for the Electrification of Redemption Hospital. This transformative project will bring reliable power to one of Liberiaโs leading healthcare institutions.
๐ง Project Features
Full electrical infrastructure upgrade
Energy-efficient systems and solar readiness
Compliance with U.S. and Liberian safety standards
Noise and air pollution control for hospital safety
๐ Environmental Protection
An Environmental Protection Plan (EPP) ensures responsible waste disposal and reduced risks.
๐งโ๐ง Community Impact
Skilled job creation and technician training.
Electrical Drawing
๐ Progress Update โ November 2025
โ Social Component
Labor supply for construction works in three (3) Districts - Gbelay Geh, Sanniquellie Mah & Zoe Gbor
Bank Account Opening for all six (6) CBOs ongoing
โ Technical Component
Procurement of tools for Gbelay Geh full completed and distributed to all CMCs
Revised BOQ and Detailed Engineering Design Completed and Submitted for review and approval
Onsite training of CMC Supervisors
Revised Full procurement plan for Nimba submitted for review & approval
Construction of VARs in Gbelay Geh - a total of 10 VARs ongoing
Gbelay Geh - Completed Construction Activities: Setting out, Clearing and de-stumping of smaller stumps
Gbelay Geh - Ongoing construction actvities: De-stumping, and full formation
Sanniquellie Mah & Zoe Gbor Ongoing Activities - Setting out & Clearing
โ Maintenance Works
Circle No. 1 completed in most districts
Finalization of IPCs preparation for payment of Old CBOs
Opening of Accounts for Old CBOs
โก๏ธ Next Steps (November 2025)
Completion of de-stumping in Gbelay Geh
Continuation of formation work in Gbelay Geh
Mobilization to Sanniquellie Mah, Zoe Gbor, and Zoe Gbao Districts
BK Enterprise, Inc TMC Nimba
Project Name: Construction of 8M Reinforced Concrete Bridge
Client: Ministry of Agriculture, TCEP I Location: Rlekporlay Town โ Bayleglay Commissioner Camp Corridor Duration: Four Weeks
๐ฏ Objectives
Construct an 8-meter reinforced concrete bridge to improve rural connectivity along the RlekporlayโBayleglay corridor.
Support agricultural development by facilitating farm-to-market access for goods and produce.
๐ง Progress (as of October 2025)
โ Casting of lean concrete for abutments โ Completed
โ Steel work & formwork for abutments and wingwall footings โ Completed
โ Casting of footing of abutments & wingwalls โ Completed
โ Steel work & formwork of abutments and wingwalls โ Completed
โ Casting of abutments and wingwalls โ Completed
โ Formwork, steelwork & casting of girders โ Completed
๐จ Steel work for slab โ Completed
๐จ Formwork for slab โ Completed
โณ Casting of slab โ Completed
โณ Finishing work (removal of form & opening of waterway) โCompleted
Bridge Works
Project Overview: Part of the Liberia Urban Resilience Project (LURP), this initiative addresses potholes, overlays, and drainage rehabilitation across Central Monrovia and Caldwell.
โ Key Activities (August 2025)
Drainage cleaning across 10 major corridors (Center St, Lynch St, Newport St, Sekou Toure Ave, Benson St, Buchanan St, McDonald St, Carey St, Camp Johnson Rd, Old CID Rd)
Solid waste collection & disposal at Whein Town landfill
Community engagement & safety toolbox talks conducted
Hazardous areas barricaded; signage installed
๐ Environmental & Social Benefits
Improved water flow, reduced flooding, safer mobility, cleaner environment, and public health benefits.
๐ฆบ Health & Safety
Zero major incidents reported
100% PPE compliance
Weekly toolbox talks & training sessions held
Drainage Cleaning โ Benson Street
BK Enterprise Inc. proudly announces the substantial completion of consulting services for the Detailed Engineering Design, Specifications, BOQ, Bidding Documents, ESIA, ESMP, and RAP of the 110KM KelipoโZwedru road corridor.
Geometric Design
Project Significance: The completion of this design project lays the groundwork for transforming southeast Liberia's infrastructure, improving regional mobility, market access, and socio-economic development.
Project Name: Saclepia to Tappita Highway (SECRAMP)
Client: Infrastructure Implementation Unit (IIU), Ministry of Public Works Consultant: SARI Consulting Ltd in association with BK Enterprise Inc. Length: ~61 km Contract Signed: November 25, 2021 Commencement Date: February 1, 2022
๐ Work Progress (as of September 6, 2025)
Clearing & grubbing: 61.33 km (100%)
Base course: 52.87 km (86.21%)
Subbase โ first layer: 60.71 km (98.9%)
Subbase โ second layer: 54.71 km (89.21%)
Subgrade: 60.71 km (99%)
Binder course: 52.80 km (86.09%)
Wearing course: 49.57 km (80.83%)
Pipe culverts: 100 (100%)
Box culverts: 13 (100%)
Road marking: Completed up to Km94 where wearing course installed
๐ Outstanding Works
The major outstanding component is the construction of Bridge No. 1 (Two-span, 2x20m) at Km40+429.
Design completed
Precast platform completed
Preparation for reinforced steel underway
Total Physical Progress: 91.32%
SaclepiaโTappita Highway Works
Strategic Impact: The road will enhance inter-county access, reduce travel time, promote trade and agriculture, and link remote regions to the national highway network.